BC Hydro Completes Construction of Interior to Lower Mainland Transmission Line

BC Hydro Line

BC Hydro’s new, high-voltage, Interior to Lower Mainland transmission line will deliver reliable power to BC’s major population centres. The 247 kilometre, 500 kilovolt power line stretches from Merritt to Coquitlam and will help bring power from where it is generated, on the Peace and Columbia rivers, to 3.2 million people on the Lower Mainland and Vancouver Island.

BC Hydro awarded the construction contract for the line in 2011 to Flatiron Graham Joint Venture, and construction began in the spring of 2012. The project includes 642 new transmission structures, as well as 500-kilovolt series capacitor station at Ruby Creek near Agassiz, and line termination work at Nicola and Meridian substations. In the process, it created more than 850 direct jobs over three and a half years of construction.

The new line was built through tough and diverse terrain in B.C.’s southern interior, crossing mountains, grasslands, major rivers, and highways.

“There haven’t been any major upgrades to our bulk transmission system in more than 30 years, and this new line is a vital link for the future,” says Bill Bennett, Minister of Energy and Mines. “Demand for power continues to grow and BC Hydro needs to be able to meet that demand and transport electricity safely and efficiently from the places like Mica generating station and the WAC Bennett dam, to major load centres.”

Jessica McDonald, President and CEO of BC Hydro, notes that BC Hydro has completed more than 550 infrastructure projects between fiscal 2011 and fiscal 2015. “Collectively, these projects were delivered more than $71 million under budget.” The final cost of the line is expected to be $743 million.

BC Hydro Line 2

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

In addition to the Interior to Lower Mainland transmission line, BC Hydro is reporting milestones for two other significant capital projects this year:

• The GM Shrum turbine replacement project at the WAC Bennett Dam was completed more than $100 million under budget. It involved refurbishing five generating units at the province’s largest facility, which will allow them to generate more power.

• The Mica 5 & 6 project will be completed later this year, within budget. BC Hydro is adding two new generating units at Mica. When the facility was built in the 1970s, it was built with four generating units and space for two more to be added in the future.

 

Related Articles


Latest Articles

  • Building a Greener Future – BuildForce Canada Report

    May 3, 2024 Retrofitting Canada’s residential, commercial, and institutional building stock to incorporate sustainable fuel sources, technologies, and materials could require as many as 57,000 additional construction workers and generate more than $81 billion in new construction investments by 2032. A new report prepared by BuildForce Canada, Building a Greener Future: Estimating the impact on construction… Read More…

  • HELUKABEL White Paper: “PUR or PVC”

    HELUKABEL White Paper: “PUR or PVC”

    May 3, 2024 The jacket material is a key factor when looking for the right cables and wires. The outer jacket performs a multitude of functions that ensure the durability, safety and performance of the cable or wire. Users must often choose between polyurethane (PUR) and polyvinyl chloride (PVC). In our new white paper “PUR… Read More…

  • Electric Avenue Annouces Improved Cold Temperature Rating of -40 Degrees

    Electric Avenue Annouces Improved Cold Temperature Rating of -40 Degrees

    April 26, 2024 Electric Avenue, a leading innovator in electric vehicle (EV) charging solutions, is thrilled to announce significant improvements to the cold temperature performance of its flagship products, the Watti Pro Lite and Watti Home Gen2. After comprehensive environmental testing, both chargers now boast an impressive operational rating of -40 degrees Celsius, surpassing the… Read More…

  • Electrical Incidents in Alberta for 2023

    Electrical Incidents in Alberta for 2023

    April 26, 2024 Regulations under the Safety Codes Act require that all electrical accidents and power line contacts be reported. This annual report by Municipal Affairs compiles a summary of incidents reported during the calendar year. Organizations in the electrical industry may wish to use this information for promoting public awareness of electrical safety risks…. Read More…


Changing Scene

  • Alberta Continues Campaign to Attract Skilled Trades People from Other Provinces

    Alberta Continues Campaign to Attract Skilled Trades People from Other Provinces

    May 3, 2024 To help fill critical job vacancies in the skilled trades, Alberta’s government has launched the third phase of the successful Alberta is Calling campaign, which is now in-market in British Columbia, Québec and Ontario. This campaign is bolstered by the Alberta is Calling Moving Bonus – a one time, $5,000 refundable tax… Read More…

  • Siemens Launches Depot360 Zero-Emission Fleet Management in Canada

    Siemens Launches Depot360 Zero-Emission Fleet Management in Canada

    May 3, 2024 With transportation being the second biggest emitter of greenhouse gases and road transport responsible for almost three quarters of these emissions globally*, Siemens Smart Infrastructure has launched Depot360, a portfolio to optimize fleet electrification. The initial focus of the solution is on logistics vehicles, municipal transit and private bus fleets within depot,… Read More…

  • Le Salon Lumen: Lumen Hosts 2024 Quebec Electrical Industry Blockbuster Customer Event

    Le Salon Lumen: Lumen Hosts 2024 Quebec Electrical Industry Blockbuster Customer Event

    (Photo caption: (From left to right) Lumen President, Serge LeBlanc, Sonepar Canada President, George McClean, Sonepar Americas President, Rob Taylor, and Sonepar CEO, Philippe Delpech in the Lumen booth, at Le Salon Lumen.) May 3, 2024 This month, Lumen held their 12th edition of the Salon Lumen, the largest exhibition in Quebec’s electrical industry. The… Read More…

  • Surgepure Announces Partnership with Focus Electrical Sales for the East Coast

    Surgepure Announces Partnership with Focus Electrical Sales for the East Coast

    May 3, 2024 SURGEPURE CORPORATION, a manufacturer of non-degrading hi-energy surge protection devices, announces a strategic partnership with Focus Electrical Sales. Based in the Maritimes, Focus Electrical Sales represents leading edge lighting and electrical manufacturers in North America. Focus adds extensive local application and technical support with offices in Nova Scotia, New Brunswick and Newfoundland,… Read More…