The Code is a comprehensive document. Sometimes it can seem quite daunting to quickly find the information you need. This series of articles provides a guide to help users find their way through this critical document. This is not intended to replace the notes in Appendix B or the explanations of individual requirements contained in the CEC Handbook** but will hopefully provide some help in navigating, while reading the code.

The 24th Edition of the CE-C, Part I, (C22.1-18)* is now available from CSA Group. This discussion of Section 78 — Marine Wharves, Docking Facilities, Fixed and Floating Piers, and Boathouses is based on the new edition.

Rule 84-000 notes that this is a supplementary or amendatory section of the code and applies only to the installation of power production sources interconnected with a supply authority system. Appendix B and the CEC Handbook have additional information and descriptions of these installations.

Rule 84-002 states that arrangements for interconnection must be in accordance with the requirements of the supply authority.

Rule 84-004 requires provision of protection against backfeed into a supply authority system fault on all interconnected electric power sources.

Rule 84-006 requires that electric power production sources be equipped with the means and equipment to establish and maintain a synchronous condition with the interconnected supply system and prevent any adverse effect.

Rule 84-008 requires that where there is a loss of voltage in one or more phases of the supply authority system, the interconnected electric power production source must be automatically disconnected and not be reconnected until normal voltage of the supply authority system is restored. An alternate procedure may be followed, if in accordance with the requirements of the supply authority. If approved by the supply authority, an inverter designed to also serve as a disconnection device that is suitable for interconnection with electric power production sources may be used.

Rule 84-010 requires that where energization of conductors and equipment is from both directions, overcurrent protection must be provided from each source of supply.

Rule 84-012 requires that the rating of overcurrent protection for a transformer that is energized from both directions is determined under Section 26, by considering first one side of the transformer and then the other side, as the primary.

Rule 84-014 requires that each interconnected electric power production source installation must have additional devices as necessary for system stability and equipment protection.

Rule 84-016 requires ground fault protection in accordance with Rule 14-102 to be provided.

Rule 84-018 requires that where an electric power production source loses voltage in one or more of its phases it must have provisions to automatically disconnect all phases from the interconnected system.

Rule 84-020 requires that all ungrounded conductors of any electric power production source of an interconnected system, be provided with a disconnecting means that simultaneously disconnects all circuits supplied by the electric power production source equipment.

Rule 84-022 requires that all ungrounded conductors of any electric power production source of an interconnected system, be provided with a disconnecting means that simultaneously disconnects all circuits supplied by the electric power production sources from the supply authority system. This provides the supply authority a single point of access to isolate one or more power production sources.

Rule 84-024 outlines the specifications that the disconnecting means must

• be capable of being energized from both sides
• plainly indicate whether it is in the open or closed position
• have contact operation verifiable by direct visible means if required by the supply authority (in accordance with 84-002, to provide added assurance to supply authority workers that the circuit is open before work is initiated)
• have provision for being locked in the open position
• conform to Sections 14, 28, and 36 if it includes an overcurrent device
• be capable of being opened at rated load
• be capable of being closed with safety to the operator with a fault on the system
• disconnect all ungrounded conductors of the circuit simultaneously
• bear a warning to the effect that inside parts can be energized when the disconnecting means is open
• be readily accessible, and
• where a main fusible disconnecting means is used, an isolating switch must be provided to allow the fuses to be dead during handling

Rule 84-026 requires that isolating means be provided to isolate equipment that is energized from both directions from all ungrounded conductors of each source of supply.

Rule 84-028 specifies that the grounding means at the service entrance may serve as the grounding means for the electric power production source in accordance with Sections 10 and 36. In the case of a dc power source connected through a solid-state inverter, the inverter must not be grounded unless the inverter ac power is separated from the supply authority system by means of an isolating transformer.

Rule 84-030 requires that a warning notice and a single-line, permanent, legible diagram of the interconnected system shall be installed in a conspicuous place at the supply authority disconnecting means of Rule 84-022 and at the supply authority meter location.

In the next instalment, we will be discussing Section 86 – Electrical Vehicle Charging Systems.

William (Bill) Burr is the former Chair of the Canadian Advisory Council on Electrical Safety (CACES), former Director of Electrical and Elevator Safety for the Province of BC, and former Director of Electrical and Gas Standards Development and former Director of Conformity Assessment at CSA Group. Bill can be reached at Burr and Associates Consulting; billburr@gmail.com

* The source for this series of articles is the Canadian Electrical Code, Part I, published by CSA.
**Note the CEC Handbook is also published by CSA.

 

Changing Scene

  • Prev
This past summer, from July 1 to September 15, AD Rewards ran the Redeem for a Dream promotion.
  Rittal Systems Canada, the world’s largest and most trusted manufacturer of ...
Learn about the latest trends in structured cabling. Offered by Fluke Networks, this seminar will ...
  After a decade of creating affordable, energy-efficient LED Lighting exclusively for the ...
Effective January 1, 2019, Ramy Yousif assumes the position of Rexel Atlantic’s General ...
Standard’s Mississauga Sales office has moved to a new location and is now fully operational. ...
Heather and Elaine Gerrie, co-presidents of Gerrie Electric, are this year’s winners of the ...
Canadian Occupational Safety magazine has announced the winners of the eighth annual Canada’s ...
After eight months, 263 events, 17 broken clocks, and thousands of competitors, Ideal’s 2018 ...
The $24 million investment by Quebec electric heating equipment and electronic controls ...

Electrician Forum Brought to you by Schneider Electric

As industry experts you know the products you use everyday better than anyone and should have input on what information you receive about products and what could improve them.

Therefore, we want your insight on the biggest challenges or issues you face when installing loadcentres, breakers (CAFI, GFI's…) and other surge protection devices. We ask that you do not provide product specific details but rather your general issues and concerns or any questions that have come to mind while working with these product types. Provide us with your valued expert insight into the issues you have faced so manufacturers can better inform you about the installation and use of these products. Lets generate some discussion that will help guide the Industry.

Make your comments  HERE

 

Codes and Regulations Brought to You by the CSA Group

  • Prev
In this article: Section 58 — Passenger Ropeways and Similar Equipment. Rule 58-000 ...
  Unauthorized CSA Group certification marks have been found on wiring by Triumph Cable ...
In this article: Section 52 — Diagnostic imaging installations. The CE code is a ...
In this article: Section 46 — Emergency Power Supply, Unit Equipment, Exit Signs, and ...
  In this article: Section 44 — Theatre Installations. The CE Code is a ...
CSA has published C22.2 No. 60947-7-3, the harmonized standard for low-voltage switchgear and ...
  Electric welders. The CE Code is a comprehensive document. Sometimes it can seem ...
  In this article: Section 40 — Electric cranes and hoists. The CE Code is a ...

 

Cloud

There has been a lot of talk about cloud computing and Software-as-a-Service (SaaS) models these days but both are relatively new to the lighting industry. Let’s take a look at what they are as well as their roles in commercial lighting.

What is cloud computing?

Cloud computing is the on-demand delivery of compute power, database storage, and applications via the Internet with pay-as-you-go or subscription-based pricing. Cloud computing means that instead of all the computer hardware, software, and data that you are using sitting somewhere inside your company’s network, it’s provided and managed for you as a service by another company and you access it over the Internet. 

Read More



Tools for the Trade

  • Prev
  IDEAL Industries has introduced Combination Drill Taps to its tool lineup. Combining the ...
  Stripping and crimping device, 100 - 240 V input voltage, for insulated ferrules with a ...
Professional all-in-one cutter/stripper for coaxial and twisted pair cables     ...
  Klein Tools' Coax Explorrer 2 tests coaxial cable and maps up to 4 locations   ...
  Ideal Industries' T-14 wire stripper s are ideal for all professionals working within the ...
  The ATS850 conveyor eliminates all types of electro static discharge requirements. ...
  Lorik Tool & Automation has the experience and ability to manufacture a variety of ...
  Ideal Industries' 26 piece insulated Journeyman kit is ideal for new electricians or for ...
  Klein Tools Deluxe Fish Rod Set comes in 19 pieces that when assembled can fish wire and ...
  BendWorks Software was designed to help electrical contractors adopt this new process ...

Product News

  • Prev
With more work being completed outside of the traditional office setting, having the right tools on ...
  Eaton has announced expanded fixtures, controls and accessories for its Halo ...
  The HALO Home Internet Access Bridge (Bridge) enables you to control your HALO Home ...
  The wireless receptacle is an integral part of the WaveLinx Wireless Connected Lighting ...
  The latest in label creation software,  Brady  Workstation has revolutionized ...
Brady’s new ToughStripe Max floor marking tape is ideal for high-traffic areas where sliding ...
  Strip, cut, twist, shear and crimp with one tool. Features four dedicated crimpers for B ...
  The ultimate in UL listed and CSA certified watertight, direct burial ...
  The IDEAL Stripmaster® Model 950™ Wire Stripper is an electrically operated, ...
   Arlington’s zinc MC cable fittings, for dry locations, are convenient and ...

 

Peers & Profiles

  • Prev
Allison Wood and Dominique Rivet are two apprentices who had a wealth of career options available ...
  In a recent sit-down Electrical Industry Canada was able to learn a little ...
David Johns is a unique and dedicated individual both at home and in the workplace. At home he is a ...
    Sean Freeman is a vibrant, enthusiastic and selfless individual who has taken his ...
  Automation companies are drivers of innovation, and have penetrated near every industry ...
Total Electrical Solutions was founded in 2013 by Jeremy Herrington in Quispamsis, on the outskirts ...
Andrew MacLeod is a territory sales manager with Leviton Manufacturing of Canada in British ...
  Floyd Lau founded Amptek Technologies in 2002 as an end to end engineering design ...
Mike Marsh, President and CEO of SaskPower, has been a leading figure in Saskatchewan’s ...
Gordon MacDonald is a cheerful, driven individual who loves to be challenged, a trait that suits ...

Copper $US Dollar price per pound


 

Jean-Marc Myette

By Line Goyette

Meeting people in our industry often comes with surprises. This was the case with Jean-Marc Myette, Business Development Manager of ABB’s Electrification Products Division and chair of the Board of Electro-Federation Canada’s Quebec section. Not only does he know the electrical industry down to the most minute product and technological innovations, he is also a professional car racer on sabbatical, and someone very involved in his business community and personal life.

Read More

 

 

Kerrwil Publications

538 Elizabeth Street, Midland,Ontario, Canada L4R2A3 +1 705 527 7666
©2018 All rights reserved

Use of this Site constitutes acceptance of our Privacy Policy (effective 1.1.2016)
The material on this site may not be reproduced, distributed, transmitted, cached or otherwise used, except with the prior written permission of Kerrwil