July 14, 2021

EIN author TerryBecker 400Terry Becker, P.Eng., CESCP, IEEE Senior Member

IEEE 1584.1 Guide for Specification of Scope and Deliverable Requirements for an Arc-Flash Hazard Calculation Study in Accordance with IEEE Std 1584 provides detailed guidance on how to complete an arc flash hazard incident energy analysis study and recommended content for the P.Eng. authenticated report.  This is a complimentary Standard to IEEE 1584.

It has been my experience in my work as an independent electrical safety consultant working in industry across Canada that not many P.Eng. Electrical Engineers are aware that the IEEE 1584.1 Guide for Specification of Scope and Deliverable Requirements for an Arc-Flash Hazard Calculation Study in Accordance with IEEE Std 1584 exists.

This is unfortunate as IEEE 1584.1 is a complimentary document to the core IEEE 1584 Standard and provides additional explanatory information and specific guidance on what content should be included in the report generated.  IEEE 1584.1 was published in 2013 to attempt to ensure that arc flash hazard incident energy analysis studies were completed correctly and with a report issued that was detailed and aligned with good engineering practice.

The IEEE 1584.1 Standard is a companion Standard to IEEE 1584 IEEE Guide for Performing Arc-Flash Hazard Calculations.  You should ensure that you have a copy of both IEEE 1584 and IEEE 1584.1 if you are performing arc flash hazard incident energy calculations and submitting reports to client.  This will allow you to substantiate any assumptions or disclaimers you may include in your report.

Currently the IEEE 1584.1 Standard is been updated from its 2013 Edition to a new Edition that will reference applicable content from the recently updated and published IEEE 1584-2018 Standard.  As is the IEEE 1584.1-2013 Standard content that is generic in nature and is applicable.  Where the updated IEEE 1584-2018 includes additional new content please ensure you reference it as a priority. 

With respect to completing arc flash hazard incident energy calculations the following steps are required to be completed in order as summarized in IEEE 1584.1:

Step 1:    Collect the system and installation data.  Start with an available Single Line Diagram.  Use specific electrical equipment data sheets.  Request Electrical Utility Fault Data for each service. Create the digital single line diagram model and enter electrical equipment data into the component editor with specific electrical equipment data in the power engineering software. Ensure you configure the “software arc flash module” and document your parameter selections before you start the incident energy analysis calculations.

Step 2:    Determine the system modes of operation.  This is a different requirement from strictly completing a short circuit analysis.  You need to consider single mode or multiple modes when determining bolted fault currents.  The number of scenarios and configurations to be considered for an arc-flash hazard analysis are dependent on the power distribution system and modes of operation (e.g., switching configurations for voltage sources, utility transformer(s), stand-alone prime power, cogeneration, emergency power generation) under normal and special conditions.

Step 3:    Short-Circuit Study.  Complete a short-circuit study that reflects the existing installation, alternate system configurations, and different operating scenarios where applicable.  Confirm electrical equipment withstand ratings.  Report any electrical equipment that is not correctly rated.

Step 4:    Protective Device Selection & Coordination Study, Time Current Curves (TCCs).  Available fault current conditions should be evaluated to determine the effect on protective device clearing times and incident energy calculations.  The existing protective devices and related settings shall be recorded as-built for existing power systems or as determined for new power systems for effective protection and coordination for system reliability.  The system design is then used to model abnormal arcing faults on specific electrical equipment and calculate incident energy and the arc flash boundary distance.  Time current curves shall be generated, referenced as required in the P.Eng. report and included for reference in the Appendices of the report issued.

Step 4:            With respect to 208V three phase electrical equipment. Previously there was a 125kVA transformer rule in IEEE 1584 2002 Edition. IEEE 1584 2018 Edition now quotes arcing faults for 208V three phase: “Sustainable arcs are possible but less likely in three-phase systems operating at 240V nominal or less with an available short-circuit current less than 2000A.” For 208V three phase 2000A available fault current is typically a 45kVA or higher transformer size depending on %Z. All panelboards sourced with a 45kVA or higher transformer where the available fault current is higher than 2000A will now require calculations. Alternately the CSA Z462 Arc Flash PPE Category Method could be applied for transformer up to 300kVA depending on impedance in %Z. Minimum recommendations are all 208V three phase energized electrical work tasks minimum 8.0 cal/cm2 Arc Thermal Performance Value (ATPV) arc flash PPE.

No incident energy analysis calculations are required for single phase 120VAC or 240VAC.

Step 5:    Determine the typical gap for the electrical equipment and enclosure sizes based upon system voltages and classes of equipment.  Reference IEEE 1584-2018 Table 8 Classes of Equipment and Typical Bus Gaps.  If you increase the gap from the default values incident energy calculated will go up.  Use typical data and no field measurements required unless electrical equipment is identified that is not typical. Verify with manufacturer’s shop drawings if available. Gap does impact incident energy calculations but is not as significant compared to other parameters.

Step 6:    Determine the box correction factor, shallow vs typical. Field measurements are not required, use typical data. Assume worst case for MCC starter buckets or other power distribution equipment that may have variable box sizes. Box correction factor doesn’t impact incident energy results significantly compared to other parameters (e.g., box/electrode configuration).

Step 7:    Determine the electrical equipment box/electrode configuration.  IEEE 1584-2018 Table 9 provides guidance of VCB, VCBB, HCB, VOA and HOA.  HCB will yield the highest calculated incident energy, then VCBB, and VCB lowest incident energy. Consider the work task description that may be performed on the electrical equipment. In some cases, two separate box/electrode configurations may be required for a single piece of electrical equipment and two separate Arc Flash & Shock Equipment Labels required for a single piece of electrical equipment.

Step 8:    Determine the working distances.  This is the anticipated distance from the arcing fault location to the Qualified Electrical Workers face and torso.  Reference IEEE 1584-2018 Table 10. Use typical working distances unless electrical equipment is unique and typical working distances are not appropriate. Increasing the working distance, lowers incident energy. If there is an application where working distance can be increased in the field by QEW then use larger working distance but document in report.

Step 9:    Calculate arcing current. Note: The system grounding does not affect the incident energy calculation as per the formulas in IEEE 1584 2018 Edition.

Step 10:  Determine the arc duration. Use the 2 Second guideline if required (adequate egress from the work task area is required and should be noted in report).

Step 11:  Calculate the incident energy at the assumed working distance for each specific location on the electrical equipment where an energized work task may be completed. You may have two calculations for a specific piece of electrical equipment if you decide to use two box/electrode configurations and related to specific energized electrical work tasks. Most likely worst-case option was utilized and would be indicated in Results Table.

Step 12:  Determine the Arc Flash Boundary distance for the electrical equipment where energized work tasks will be completed.

Step 13: Draft and issue P.Eng. Stamped Report.  See below for guidance and specifically reference IEEE 1584.1.

As identified in IEEE 1584.1 the recommended content of the P.Eng. Stamped Report would include:

  1. Eng. Stamped Cover Page.
  2. Executive Summary.
  3. Scope of Study & Results Summary.
  4. Disclaimer & Notes.
  5. Background Information. Requirement for completing the incident energy analysis as a method to determine “Additional Protective Measures” specifically arc flash PPE and the Arc Flash Boundary distance as outlined in CSA Z462 Clause 4.3.5.6 and CSA Z462 Clause 4.3.5.5. Additional information can be summarized here with explanation such as system modes of operation (e.g., single or multiple) that were short listed and utilized in completing the short circuit and arcing fault current calculations.  Analysis software used and configuration settings.
  6. Review of System Data.  Identify basis of electrical equipment data used to create the power system model, utility available fault currents, cable sizes, motor data and the motor hp cut off for using the lumped load feature in the power system analysis software (e.g. <200hp). 
  7. Any data assumptions made shall be listed. Include AutoCAD single line diagrams and data sheets in Appendix of report.
  8. Short Circuit Analysis Results. Summarize the basis for the calculations and findings. Identify if any electrical equipment was found to be outside of its current withstand ratings.
  9. Protective Device Coordination Study. Review the findings and discuss results and reference applicable Time-Current-Curves. Discuss basis for any potential changes to protective device settings to lower incident energy and ensure any implications are documented.
  10. Arc Flash Hazard Incident Energy Analysis. List the results of the base incident energy calculations with existing power system configuration in a summary table in the body of the report. Make recommendations for incident energy reduction.  There is no 40 cal/cm2 “Dangerous” incident energy level, where “No PPE Exists.”  This information was included in the power system software and historically has been used in error.  Incident energy doesn’t correlate directly to arc blast pressure.  You can have higher incident energy levels at lower available fault currents and on low voltage equipment over high voltage electrical equipment.  Technically incident energy over 140 cal/cm2 is high risk energized electrical work as there is no available arc-rated clothing greater than 140 cal/cm2 ATPV (e.g., Oberon Company).  The arc flash calculations results table should not include any reference to HRC #, Cat #, Level # or “letter” for arc flash PPE related to the incident energy results. 
  11. With respect to any recommendations made and documented in the report related to Arc Flash & Shock Equipment Labels the content on the label needs to meet the minimum requirements identified in CSA Z462 Clause 4.3.5.7 and the presentation of the information and use of signal pane wording should comply with ANSI Z535.  The Equipment Label should not include any reference to HRC#, Cat #, Level # or “letter” for arc flash PPE, the employer will define the arc flash PPE they provide to their workers.  CSA Z462 Workplace electrical safety Standard, Annex Q Arc flash and shock equipment labels, Figure Q.3 illustrates a compliant arc flash & shock equipment label.
  12. Recommendations for Incident Energy Reduction.  Advise client for Management of Change purposes recommended protective device setting changes.  Where required provide cost benefit analysis of any other incident energy reduction methods that are technically feasible 
  13. (e.g., arc flash relay, maintenance mode switch, more complex relaying schemes, IR scanning windows, etc.). Establish a realistic incident energy target level (e.g., 75 cal/cm2).
  14. Conclusion
  15. Appendices include AutoCAD single line diagram, analysis software single line diagram, field data sheets, provided utility short circuit data report, short circuit analysis report, TCCs, arc flash incident energy analysis results table(s), example Arc Flash & Shock Equipment Labels. Anything else?

Based on my experience in reviewing Arc Flash Hazard Incident Energy Analysis Reports for clients across Canada many of the reports I have reviewed were deficient in content and included errors & omissions based on the detailed requirements and basis of the incident energy calculations as documented in IEEE 1584.  With the new updated 2018 Edition of the IEEE 1584 Standard it will be even more important that the responsible P.Eng. Electrical Engineer documents in detail the assumptions made, any disclaimers, field data validation, etc..

It is also extremely important that any Arc Flash & Shock Equipment Label recommendations provided to a client in a report meet the minimum requirements of Equipment Labeling as identified in CSA Z462 Workplace electrical safety Standard, Clause 4.3.5.7 and also reference CSA Z462 Annex Q Arc flash and shock warning and information labels as noted above.  It is important to note that the “Danger” signal pane should only be used if the calculated incident energy is greater than 140 cal/cm2 NOT 40 cal/cm2.  Make sure the footer of the label indicates the protective device ID and location of the incident energy (e.g. load side, line side or bus).

This article is a simplified summary of the IEEE 1584.1 Guide for Specification of Scope and Deliverable Requirements for an Arc-Flash Hazard Calculation Study in Accordance with IEEE Std 1584.  You are advised to purchase a copy of IEEE 1584.1 and review its content in detail when completing your incident energy analysis study and drafting the report that is issued to clients.

Terry Becker, P.Eng., Certified Electrical Safety Compliance Professional (CESCP), IEEE Senior Member is the first past Vice-Chair of the CSA Z462 Workplace electrical safety Standard Technical Committee and currently a Voting Member and Clause 4.1 and Annexes Working Group Leader.  Terry is also a Voting Member on the CSA Z463 Maintenance of electrical systems Standard and a Voting Member of the IEEE 1584 Guide for Performing for Arc-Flash Hazard Calculations.   Terry has presented at Conferences and Workshops on electrical safety in Canada, the USA, India and Australia.  Terry is a Professional Engineer in the Provinces of BC, AB, SK, MN and ON.  Terry is an Electrical Safety Specialist, Management Consultant at TW Becker Electrical Safety Consulting Inc., and can be reached at 1-587-433-3777 or by email terry.becker@twbesc.ca.

Changing Scene

  • Prev
Last week's disastrous floods have left many B.C. residents homeless, stranded or in desperate need ...
The Canadian Apprenticeship Forum (CAF-FCA) will launch a new program to empower skilled trades ...
Sean Dunnigan, President of Techspan Industries Inc., is pleased to announce the appointment of ...
The Electrical Safety Authority (ESA) would like to advise that the Minister of Government and ...
LabTest Certification Inc. is proud to announce its most recent recognition by OSHA as a Nationally ...
On November 13th, the Universal Women’s Network virtually hosted the 2021 Women of ...
Soussanna Karas, Director of Licensing at ESA, breaks down the risks of the underground economy ...
BCEA U40 group invites you to their Professional Development virtual series...     ...
Three accomplished women with diverse backgrounds are the newest members of Ontario Power ...


 

EIN ABB logo 400ABB is an international company with a large global presence, but did you know that a significant percentage of the products sold in Canada are also designed and manufactured locally?

ABB’s Installation Products division, formerly known as Thomas & Betts, operates seven manufacturing facilities in Canada, six of them in Quebec and one in Alberta.

Many of their most well-known brands, including IBERVILLE®️️, Marrette®️️, Microlectric®️️, and Star Teck®️️, are products that started in Canada and are still manufactured locally to meet Canadian standards.

 

 


 

Canadian Electrical Contractor Discussion Group: Can You Count the Deficiencies?

EIN CECD 400Have you ever been called to fix the work of a 'handyman'?

"Was supposedly done by a"certified ' electrician....told the homeowner that he got a $266 permit....no record at TSBC. Can you count the deficiencies?"

"There is a second panel change in the triplex also.......even more deficiencies. Think the guy was a glorified handyman. Ones not obvious: 240 BB heat hooked up 120....drier on 2p20....range on 2p50....water heater fed with 2c14 Bx on 2p15."

Go HERE to join the discussion

 


 



 

 Siemens Built In Isolation Products 400By Alyssa Kerslake

Life safety today is top of mind for nearly everyone. There is a certain level of trust that fire alarm systems continue to work within a fire incident. With system survivability being a key concern to regulators, building managers, and the public, Siemens has developed systems that are designed to meet and exceed regulations that protect people, property, and assets. 

One of the most significant concerns, particularly in a large multi-story building, is implementing a secure and fully functional fire alarm system. Today, it is not uncommon to have power and data for hundreds of fire alarm devices connected over a single pair of wires. The concern is, if a fault occurs somewhere between the devices, the zone and location of the device may no longer be known, or the operation of that circuit reduced or possibly impaired. These scenarios could allow an undetected catastrophic event to develop within the space due to inoperable life safety devices. 

 

Read More


 

 

David Gordon

By Terry Becker, P.Eng., CESCP, IEEE Senior Member

The CSA Z462 Workplace electrical safety Standard published its 2021 Edition in January.  A mandatory requirement for an employer is developing, implementing, and auditing an Electrical Safety Program.  If you have an Electrical Safety Program, is it up to date in its policies, practices and procedural requirements, is it performing as expected?  Workers do not necessarily do what you expect, they do what you inspect!  Management of change is required.

I have been involved in supporting industry with respect to shock and arc flash hazards in the workplace and in understanding what needs to be done to ensure worker safety, that effective defendable due diligence is established, and evidence of compliance is available related to occupational health & safety regulations both Provincial, Territorially or Federally.  I am in Ontario this week completing a detailed Electrical Safety Audit at multiple enterprise facilities.


Read More


 

Product News

  • Prev
On the hottest days of the summer and the coldest of the winter, the Napoleon NS18 heat pump and ...
Lumenwerx is pleased to launch Aera, an innovative lighting family that marks a new era in recessed ...
Eaton’s humidity sensor and fan control (HDFS3P1) device is a single pole humidity sensor for ...
With an EC motor and smart control, ORA-EC40 series air curtains are ideal for commercial and ...
Klein Tools expands its line of insulated screwdrivers with new lengths and tips, as well as a new ...
EarthTronics LED High Lumen Wattage & Color Selectable Series to provide flexibility and full ...
Eaton’s astronomic programmable timer (AT18HM) device reduces energy consumption by automating ...
The HomeGuard LED family of residential security lights, with rugged die cast aluminum ...
This preassembled constant wattage heating cable from Ouellet is specialized for roof and gutter ...


 

Milwaukee M12 Cable Stripper

Connect plug-in lamps, holiday lighting, and small appliances to the top “Controlled” outlet, while the bottom “Powered” outlet remains always on. The DW15R features tamper resistant receptacles with built-in shutters to prevent the insertion of unintended foreign objects. As well, the integrated button with vanishing feedback LED provides manual push-button on/off control and clear indiciation at any time.

Simplify control of the residence - schedule lamps and connected loads to turn on/off at specific times or based on sunrise/sunset, easily group smart devices into rooms, and create scenes to activate multiple loads at once. Utilize the auto-shutoff feature as a countdown timer in closets, hallways and bathrooms.

Read More


 

 

Incoplas Hybrid

Now available for Siemens Class 52 Actuators and Indicator Lights are the new Class 1, Div. 2 contact blocks. Suitable for use in Hazardous Location, Class 1, Div. 2 applications when used in a suitable enclosure. No matter which style actuator you use, the common base provided attaches to the hazardous location contact blocks easily.

Hazardous Location (HL) Series Contact Blocks are good for Hazardous Location CL1, DIV2 Applications using a Standard Enclosure NEMA 1, 12, 13, 4, 4X.

HL Series Contact Blocks are rated for switching high inrush loads like Tungsten Lamps.

 

Read More


 

 

EarthTronics 25-Watt Emergency Driver for Linear Highbay

The 20A Outlet and 15A Outlet have the ability to allow function specific Inserts to be installed/removed/swapped making this platform an optimal choice for renovations and new construction. The Swidget Outlet is installed using the same wiring as a standard wall receptacle and when paired with a Swidget Insert turns into a powerful and flexible Smart Home device. The swapability of the Inserts ensures that this will work with Smart Home wireless systems now and in the future.

The Swidget product line targets the Home Automation and Smart Home markets with a unique future-proof solution. Swidget currently offers eight smart Inserts with different functionalities including Wi-Fi control, indoor air quality sensor, temperature, humidity, and motion sensors, as well as a USB charger guide light, and emergency lighting. They can all be controlled from anywhere with the Swidget App for iOS/Android or Alexa and Google Home.

Read More


 

Peers & Profiles

  • Prev
Allana Kellett-Jamieson loves working in the electrical sector and is proud of the great focus ...
As the head of ABB Canada's electrification business unit, Éric Deschênes is no newcomer to the ...
Karen Pullen knows what it’s like to be the only woman on a construction site, and as a proud ...
As of February 2021, Martin Stephenson is the new President and CEO of Signify Canada.   ...
This past July, Kerith Richards, who has worked for Service Wire Company for the last seven years, ...
EngWorks was formed in 2004 as an electrical engineering and consulting firm by Allan Bozek, “After ...
Headquartered in Concord, Ontario, Mercury Lighting services national retail, ...
Among the recipients of the 2021 Clean50 Awards announced last month is Carolina Gallo, Vice ...
Sarah Silverstein is a principal with Liteline along side her two brothers Mark and Daniel. ...
As a 34-year-old female owner of an electrical contracting business, Danielle Gray may be unique. ...


EngWorksBy Blake Marchand

EngWorks was formed in 2004 as an electrical engineering and consulting firm by Allan Bozek, “After a short time we realized there was a niche in hazardous locations, in particular in hazardous area classification design requirements for various facilities. And also helping people understand just how the Canadian Electrical Code applies to hazardous locations.”

Given the complexity of hazardous locations, Bozek saw a need for education while working in the field and began developing training courses designed.

Read More


 

Éric DeschênesBy Line Goyette

As the head of ABB Canada's electrification business unit, Éric Deschênes is no newcomer to the electrical industry. He has a long track record and a passion for finding practical solutions to optimize technology adoption. Deschênes took on his current role with ABB January of 2020, he joined ABB in 2017 as Executive VP of the Electrification business after 15 years with Schneider Electric.

We met with him recently to discuss his new role at the helm of ABB Canada and his plans moving forward. He began by pointing out that the recent change to ABB Canada's structure, as elsewhere in the world, was made to make customer relations more straightforward. 

Read More


 

Copper $US Dollar price per pound

Kerrwil Publications Great Place to Work. Certified December 2019 - December 2020

538 Elizabeth Street, Midland,Ontario, Canada L4R2A3 +1 705 527 7666
©2021 All rights reserved

Use of this Site constitutes acceptance of our Privacy Policy (effective 1.1.2016)
The material on this site may not be reproduced, distributed, transmitted, cached or otherwise used, except with the prior written permission of Kerrwil