Case Study: Temporary Power for Large Scale Residential Construction

Temporary Power

Ever wonder how large construction projects with sales offices and show suites get power when there is only a generator or temporary power established on the construction site?TheBC Safety Authority (BCSA) pays close attention to these types of installations, since fire alarms, sprinklers, and other building code safety systems are not up and running during the construction phase of the project.

Recently, a BCSA safety officer conducted an assessment of a large multi-family residential site under construction. Working collaboratively with electrical contractors, other trades, safety officials, utilities, and building departments to reach safety solutions is an important part of a BCSA safety officer’s role.

During the inspection, several significant hazards were found.Most notably, townhouses had been energized using the temporary construction service, creating a risk of overload to the service. Had these dwellings become occupied, this could have resulted in a serious fire and shock hazard.

An additional hazard was created by the power cable used to provide power from the temporary distribution system to the townhouses, which was not installed with the necessary mechanical protection.Construction sites typically have heavy machinery operating and it is imperative that the power cables be installed in a manner that protects them from mechanical damage.A break in the armoured cable can result in either a fire (if combustible material is near by) or a shock hazard if the bonding provisions have been compromised.

Addressing the hazards
The safety officer first documented his findings in a certificate of inspection and contacted the electrical contractor to develop a plan to rectify the identified non-compliances.The contractor submitted an application for a variance, as required by the Safety Standards Act, to energize the show rooms and sales offices.The variance included a request to energize a specific portion of the site, and outlined the wiring method used to provide power to this area of the site, and the signage required at strategic locations on the site, including mark ups on the site’s safety plans.The safety officer granted the variance and the electrical contractor completed the installation and the obligations outlined in the variance.

To reduce the safety hazards on the site, branch circuits inside each dwelling had all unnecessary circuit conductors disconnected from circuit breakers. The heavy loads such as space heating, furnaces, dryers, ranges were also disconnected.The safety officer then informed BC Hydro and the electrical contractor that a “hold connection” be placed on the permanent installation permit.This ensures that when the permanent installation is ready for power, the necessary work is completed to transfer and disconnect the temporary power in the showrooms to remove the risk of a possible back feed.

When dealing with sites that have both permanent and temporary electrical systems, closely review your electrical code, specifically the stating that interconnection of temporary power installations and permanent installations shall not be interconnected unless by special permission.

This article was first published online by the BC Safety Authority, http://safetyauthority.ca.

 

Related Articles


Latest Articles

  • Future-Proofing your Business with Electrical Estimating Software

    Future-Proofing your Business with Electrical Estimating Software

    In today’s construction landscape, it’s crucial for construction business owners to seize every opportunity to future-proof their operations. Building a thriving electrical (or mechanical) contracting company entails more than just acquiring technical skills and setting up a business. Read More…

  • Ontario Drives Monthly Downturn in Residential Sector for March 2024 Building Permits

    Ontario Drives Monthly Downturn in Residential Sector for March 2024 Building Permits

    May 16, 2024 Month over month, the total value of building permits in Canada decreased 11.7% to $10.5 billion in March. Construction intentions in the non-residential component declined 16.7% to $4.0 billion, while the residential sector decreased by 8.3% to $6.5 billion. Declines were observed in all components except for the commercial component. On a constant dollar basis (2017=100), the total… Read More…

  • 25th Edition of the MEET Show Smashes Attendance Records

    25th Edition of the MEET Show Smashes Attendance Records

    May 16, 2024 By Electro-Federation Canada The energy and excitement was palpable at the 2024 edition of the MEET Show at the Moncton Coliseum on May 1 and 2. The biennial Mechanical, Electrical, Electronic, and Technology show – celebrating its 25th year in 2024 – saw record-breaking attendance, welcoming 6,626 industry professionals to one of… Read More…

  • Video: How to Easily Setup and Program Intermatic PE700 Series Wireless Timers

    Video: How to Easily Setup and Program Intermatic PE700 Series Wireless Timers

    May 10, 2024 Dive into the future & discover the ultimate convenience in pool & spa management with this “How to” video guide for setting up & programming the PE700 Series Pool & Spa Wireless Smart Timer, by Intermatic. Whether you are programming the 3-circuit model PE733P or the 2-circuit PE723P, this video is your… Read More…


Changing Scene

  • WOW Lighting and Controls adds Blink Charging to Line Card

    WOW Lighting and Controls adds Blink Charging to Line Card

    May 17, 2024 WOW Lighting and Controls are excited to introduce the newest addition to the Wow Lighting and Controls linecard: Blink Charging Co. Blink Charging Co. (Nasdaq: BLNK) is a global leader in electric vehicle (EV) charging equipment and services, enabling drivers, hosts, and fleets to easily transition to electric transportation through innovative charging solutions. Blink’s… Read More…

  • Join ECABC’s Call for Prompt Payment in BC

    Join ECABC’s Call for Prompt Payment in BC

    May 17, 2024 On Monday, May 6th, ECABC launched a campaign across its social media platforms to create awareness for the need for prompt payment laws in British Columbia, now. Year after year, BC’s lack of prompt payment has been the #1 issue for ECABC’s contractors. Why? Because prompt payment ensures that contractors and subcontractors receive… Read More…

  • ABB Invests in Ndustrial to Accelerate Decarbonization Through AI-Powered Energy Management Technologies

    ABB Invests in Ndustrial to Accelerate Decarbonization Through AI-Powered Energy Management Technologies

    May 17, 2024 ABB today announced a minority investment in Ndustrial, a US-based clean technology startup that has developed a leading-edge, AI-powered energy management platform. This innovative technology enables smarter, production-aware energy decisions in real time, helping customers reduce operating costs, optimize energy consumption and accelerate decarbonization. The investment was made through ABB Ventures. Financial… Read More…

  • Legislative Amendments Aim to Improve Benefits for Injured Workers in New Brunswick

    Legislative Amendments Aim to Improve Benefits for Injured Workers in New Brunswick

    May 17, 2024 The provincial government has introduced legislative amendments meant to improve benefits for injured workers and their families while ensuring sustainability of the workers’ compensation system. The changes, if approved, would apply to the Workers’ Compensation Act and the Firefighters’ Compensation Act. “We are proud to introduce changes that will see the amount payable to injured… Read More…